WOW! Things are changing daily now! This is the new "D Dock" ( "A Dock" 
is the southern most dock) and it's almost completely in place. The pile driver
is just beginning to  work on this piling. The top is just about even with the top
of the building in the background

 


                                                                                                          Phil Briggs photo
This is the same piling almost all the way in. A puff of smoke can be seen about
half way up the left side of the pile driver as it had just made a stroke.


These are C & D Piers in place.


B Pier on the right and C on the left.


The Pile driver placed all of the piles on D Pier except the very outboard one.
Apparently they fought the wind all day. The contractor is trying to maintain less
than 1/2 inch  positional accuracy in setting the pilings. That's pretty good!


                                                                                                              
A Phil Briggs photo
Apparently the wind was pushing the barge against the new pier. This fellow is 
trying to push the barge away. I don't think he was very effective.


Much of the backfilling has been completed. If you see this now, you will 
notice this has been done only out to the old bulkhead. The space between
 the old bulkhead and the new one will be filled once the electrical and 
plumbing work has been completed.

Next week should be real exciting. Phil tells me all of the different 
contractors will be busy doing their thing. Another dock will be arriving 
as well as the finger piers. The electrical folks will be starting their phase 
of work as well as the plumbers.

Sit tight folks, This will be a fun ride!